R.A. 9184 is the Government Procurement Reform Act of 2003. It makes competitive bidding the rule for all government procurement of goods, infrastructure projects and consulting services, puts a Bids and Awards Committee in every procuring entity, lays out the bidding stages from the Annual Procurement Plan to the Notice to Proceed, and allows five alternative methods only under stated conditions. The exam asks about the governing principles, the BAC's size and term, the deadlines in the award stage, the thresholds for shopping and repeat orders, where protests go, and the penalties.
The Act has seventy-eight sections in twenty-five articles, and much of the detail is left to the implementing rules. What the statute itself fixes is the structure: the principles, the definitions, the planning and electronic-procurement rules, the BAC, the bidding sequence, the award deadlines, the alternative methods and their conditions, the protest route, the Government Procurement Policy Board and the penalties. Those are what questions test, and those are what this guide covers; it does not walk every section.
The guide follows the law in order. Each part says what the section requires in plain language, lists the facts questions turn on, and shows how many of the bank's sourced questions test it, with one of them worked through.
Written from the text of R.A. 9184 as published by Arellano Law Foundation (LawPhil Project). 58 of the bank's practice questions are tied to a section of it.
R.A. 9184 at a glance: the numbers questions turn on
What
Rule
Where
Governing principles
Five: transparency, competitiveness, a streamlined process, accountability, public monitoring
Section 3
The default method
Competitive Bidding, except as Article XVI allows
Section 10
BAC size and chair
At least 5 and not more than 7 members, chaired by at least a third ranking permanent official other than the head
Section 11
BAC term
1 year from appointment, renewable
Section 11
BAC observers
The COA representative plus at least 2 observers: one from a private group in the relevant sector, one from an NGO
Section 13
BAC honoraria
Not exceeding 25% of basic monthly salary
Section 15
Ceiling on bid prices
The Approved Budget for the Contract; no lower limit
Section 31
Head of entity acts on the BAC's recommendation
Within 15 calendar days
Section 37
Winning bidder signs the contract
Within 10 calendar days from receipt of the Notice of Award
Section 37
Notice to Proceed
Not later than 7 calendar days from approval of the contract
Section 37
Bid opening to award
Not more than 3 months
Section 38
Repeat order limits
Within 6 months of the Notice to Proceed; not more than 25% of each item's quantity
Section 51
Shopping limits
P50,000 for an unforeseen contingency; P250,000 for ordinary office supplies, with at least 3 quotations
Section 52
Bidder relation to the head of the entity
Sworn affidavit of no relation within the third civil degree
Section 47
Criminal penalty
Imprisonment of 6 years and 1 day to 15 years
Section 65
Administrative penalty on bidders
Suspension of 1 year for the first offence, 2 years for the second
Principles, scope, planning and electronic procurement
Sections 1 to 4 name the Act, state the policy of good governance, lay down the five governing principles that all government procurement must follow in all cases, and set the scope: the procurement of Infrastructure Projects, Goods and Consulting Services, regardless of source of funds, by all branches and instrumentalities of government including GOCCs and local government units, subject to Commonwealth Act No. 138 and to treaties the Philippines has signed.
Section 7 ties procurement to the budget: nothing is procured unless it is in the Annual Procurement Plan, which the Head of the Procuring Entity approves and which must match the approved yearly budget. Sections 8 and 9 make the Government Electronic Procurement System (G-EPS) the single portal and primary source of information on government procurement, with an audit trail the Commission on Audit may verify. Section 10 states the rule the rest of the Act works from: all procurement is by Competitive Bidding, except as Article XVI provides.
•The five principles: transparency; competitiveness; a streamlined process that applies uniformly; a system of accountability for public officials and private parties alike; and public monitoring.
•The Act covers Infrastructure Projects, Goods and Consulting Services, whether the funds are local or foreign, and covers GOCCs and local government units.
•No procurement may be undertaken unless it is in the approved Annual Procurement Plan; for infrastructure, the plan includes engineering design and acquisition of right-of-way.
•The G-EPS is the primary and definitive source of information on government procurement, and all Procuring Entities use it for common supplies.
•The G-EPS must provide an audit trail and let the Commission on Audit verify its security and integrity at any time.
•All procurement is done through Competitive Bidding, except as provided in Article XVI (the alternative methods).
3 practice questions in the bank test this part.
A practice question on Section 3
Which principles govern all government procurement under R.A. 9184?
APreference for the largest contractor available
BSpeed and confidentiality above all
CTransparency, competitiveness, a streamlined process, accountability, and public monitoring (correct)
DDiscretion of the agency head in every case
Section 3 sets out the governing principles: transparency in the process and in contract implementation, competitiveness by extending equal opportunity to eligible private parties, a streamlined process applying uniformly to all government procurement, a system of accountability, and public monitoring.
“Transparency in the procurement process and in the implementation of procurement contracts”
The defined terms and the Government Procurement Policy Board
Section 5 defines fifteen terms. The ones that recur are the Approved Budget for the Contract (ABC), the BAC, Competitive Bidding and its six processes, the three kinds of procurement (Goods, Infrastructure Projects and Consulting Services), the Head of the Procuring Entity, and Procurement itself, which includes the lease of goods and real estate. Section 6 standardises the process and the forms through manuals the GPPB issues, which are mandatory once issued.
Sections 63 and 64 establish the Government Procurement Policy Board (GPPB) and fix its membership: the Secretary of Budget and Management as Chairman, the Director-General of NEDA as Alternate Chairman, eleven named department secretaries, and a private-sector representative appointed by the President. Section 75 gives the GPPB sixty days from promulgation of the Act to formulate the implementing rules jointly with the Joint Congressional Oversight Committee created by Section 74, for the President's approval.
•The ABC is the budget for the contract approved by the Head of the Procuring Entity (national agencies), the governing board (GFIs and state universities) or the Sanggunian (LGUs).
•Competitive Bidding has six processes: advertisement, pre-bid conference, eligibility screening, bid evaluation, post-qualification and award of contract.
•Goods are all items, supplies, materials and general support services other than consulting services and infrastructure projects, including janitorial, security, trucking and hauling services.
•Consulting Services need external technical and professional expertise beyond the government's capability: advisory and review services, feasibility studies, design, construction supervision, management services and special studies.
•The Head of the Procuring Entity is the head of the agency, the governing board of a GOCC, or the local chief executive of an LGU.
•Procurement includes the lease of goods and real estate; real property acquisition is governed by R.A. 8974.
•GPPB: chaired by the Secretary of Budget and Management, with the NEDA Director-General as Alternate Chairman; it formulates and amends the IRR and standard forms, and may invite a COA representative as resource person.
•The IRR were due within 60 days of promulgation, formulated by the GPPB with the Oversight Committee and approved by the President; standard forms within 30 days after that.
2 practice questions in the bank test this part.
A practice question on Section 64
Who chairs the Government Procurement Policy Board under Section 64 of R.A. 9184?
AThe Secretary of the Department of Budget and Management (correct)
BThe Director-General of the National Economic and Development Authority
CThe Chairperson of the Commission on Audit
DThe Secretary of the Department of Public Works and Highways
Section 64 composes the GPPB with the Secretary of the Department of Budget and Management as Chairman and the Director-General of the National Economic and Development Authority as Alternate Chairman.
“the Secretary of the Department of Budget and Management, as Chairman”
Section 11 requires each procuring entity to establish a single BAC, with separate or lower-level BACs where the number and complexity of items warrant. Its members are designated by the Head of the Procuring Entity, who may never be a member, and serve a fixed term of one year, renewable. Section 12 gives the BAC its functions - advertising, pre-procurement and pre-bid conferences, eligibility, receipt and evaluation of bids, post-qualification, and recommending the award - and lets it create a Technical Working Group and recommend alternative methods.
Section 13 opens the BAC's proceedings to observers at all stages. Section 14 gives it a Secretariat, Section 15 allows honoraria, and Section 16 tasks the GPPB with a sustained training programme to professionalise BACs, Secretariats and Technical Working Groups.
•The BAC has at least 5 and not more than 7 members, chaired by at least a third ranking permanent official of the entity other than its head.
•The approving authority is in no case a member of the BAC.
•Members serve a fixed term of 1 year from appointment, renewable at the discretion of the Head of the Procuring Entity; a replacement serves only the unexpired term.
•If the Head of the Procuring Entity disapproves the BAC's recommended award, the disapproval must rest on valid, reasonable and justifiable grounds expressed in writing, copy furnished the BAC.
•The BAC prepares a procurement monitoring report submitted to the GPPB on a semestral basis.
•Observers at all stages: the Commission on Audit representative plus at least 2 others, one from a duly recognised private group in the relevant sector and one from an NGO, both registered with the SEC and without interest in the contract.
•Honoraria to BAC members may not exceed 25% of their basic monthly salary, under DBM guidelines and subject to funds.
8 practice questions in the bank test this part.
A practice question on Section 11
How many members must a Bids and Awards Committee have under Section 11 of R.A. 9184?
AExactly three
BAt least seven but not more than eleven
CAt least five but not more than seven (correct)
DAny number the head of the procuring entity chooses
Section 11 requires each procuring entity to establish a single BAC with at least five members but not more than seven.
“The BAC shall have at least five (5) members, but not more than seven (7) members.”
Section 17 lists what the Bidding Documents must contain, from the ABC and the instructions to bidders through the terms of reference, specifications, the forms and amounts of bid and performance security, and the form of contract. Section 18 bars references to brand names in specifications for Goods, and Section 19 forbids releasing any part of the Bidding Documents to any prospective bidder before their official release.
Section 20 makes a pre-procurement conference mandatory for every procurement before the Invitation to Bid is issued, except for contracts below an amount set in the IRR. Section 21 requires the Invitation to Bid to be advertised as widely as the circumstances need - in the entity's premises, newspapers of general circulation, the G-EPS and the entity's website - and lists its contents. Section 22 requires at least one pre-bid conference per procurement.
•Bidding Documents follow the GPPB's standard forms and include the ABC, instructions to bidders, terms of reference, eligibility requirements, plans and specifications, the bid form, delivery or completion schedule, bid security, performance security and warranty, and the form of contract.
•Specifications for Goods are based on characteristics and performance; reference to brand names is not allowed.
•Before official release, no aspect of the Bidding Documents may be divulged to any prospective bidder.
•The pre-procurement conference confirms the certification of availability of funds and reviews the documents and draft Invitation to Bid; it is optional only for contracts below the IRR threshold.
•The Invitation to Bid states the ABC, the source of funds, the contract duration, the deadlines, and where the Bidding Documents may be secured.
•At least one pre-bid conference is held for each procurement, and one may be called on a prospective bidder's written request subject to BAC approval.
4 practice questions in the bank test this part.
A practice question on Section 18
A draft specification for office printers names a particular manufacturer's model. What does Section 18 of R.A. 9184 require?
AThat the brand name be approved by the GPPB
BThat at least three brand names be listed
CThat reference to brand names not be allowed, with specifications based on characteristics or performance requirements (correct)
DThat the brand be of Philippine manufacture
Section 18 requires specifications for the procurement of goods to be based on relevant characteristics or performance requirements, and states flatly that reference to brand names shall not be allowed.
Receipt, opening, evaluation and post-qualification of bids
Sections 23 and 24 cover eligibility: for Goods and Infrastructure Projects the BAC checks compliance with the eligibility requirements, certified under oath; for Consulting Services eligible bidders are further rated numerically to produce a short list. Sections 25 to 29 cover the bids themselves - two components in separate sealed envelopes submitted simultaneously, a deadline after which nothing is accepted, modification and withdrawal before the deadline, a bid security, a validity period, and public opening.
Sections 30 to 34 are the evaluation sequence. A pass/fail check of the technical component comes first; the ABC is the ceiling and there is no floor; financial bids for Goods and Infrastructure are ranked from lowest to highest to find the Lowest Calculated Bid, while consulting bids are ranked by rating to find the Highest Rated Bid; then post-qualification verifies that bidder, and if it passes its bid becomes the Lowest Calculated Responsive Bid or Highest Rated Responsive Bid. Section 35 defines a failure of bidding and Section 36 allows award to a single responsive bid.
•A bid has two components, technical and financial, in separate sealed envelopes submitted simultaneously; bids after the deadline are not accepted.
•A bidder who withdraws before the deadline may not submit another bid for the same contract, directly or indirectly.
•The bid security guarantees that the winning bidder will enter into the contract and furnish the performance security; the BAC opens all bids publicly.
•Preliminary examination uses pass/fail criteria on the technical component; only complete bids have their financial component opened.
•The ABC is the upper limit for bid prices - bids above it are disqualified outright - and there is no lower limit to the amount of the award.
•Goods and Infrastructure: ranked lowest to highest, the lowest is the Lowest Calculated Bid. Consulting Services: ranked by numerical rating, the highest is the Highest Rated Bid, after which the entity negotiates with the first-ranked bidder, then the second if that fails.
•Post-qualification turns the Lowest Calculated Bid into the Lowest Calculated Responsive Bid, or the Highest Rated Bid into the Highest Rated Responsive Bid; a bidder that fails is post-disqualified and the next-ranked is examined. The contract is awarded only to the LCRB or HRRB.
•Failure of bidding: no bids received, no bid qualifies as the LCRB, or the winning bidder refuses the award without justifiable cause. The contract is re-advertised and re-bid; after the second failed bidding the BAC may resort to negotiated procurement.
15 practice questions in the bank test this part.
A practice question on Section 24
What must a prospective bidder for consulting services certify under R.A. 9184?
AThat its price is the lowest in the market
BThat it has never bid before
CUnder oath, the correctness of the statements made and the completeness and authenticity of the documents submitted (correct)
DThat it employs only Filipino citizens
Section 24 requires the prospective bidder to certify under oath as to the correctness of the statements made, and the completeness and authenticity of the documents submitted, as part of the eligibility requirements for consulting services.
“The prospective bidder shall certify under oath as to the correctness of the statements made, and the completeness and authenticity of the documents submitted”
Section 37 is the most-tested section of the Act, because it is a chain of calendar-day deadlines: the Head of the Procuring Entity acts on the BAC's recommendation, issues the Notice of Award, the bidder signs the contract, a higher approving authority or a GOCC board approves it, and the Notice to Proceed goes out. Section 38 caps the whole process from bid opening to award at three months, and deems a contract approved if the head or board does not act within the periods in Section 37.
Section 39 requires a performance security before signing; Section 40 says what happens when the winning bidder fails to sign or post it; Section 41 reserves to the head of the agency the right to reject all bids for collusion, BAC failure to follow procedure, or any justifiable ground. Sections 43 to 46 allow preference for domestic goods, apply the bidding rules to provincial projects and to equipment leases, and give provincial contractors a matching privilege for five years. Section 47 requires every bidder to swear that it is not related to the Head of the Procuring Entity.
•The Head of the Procuring Entity approves or disapproves the BAC's recommendation within 15 calendar days of the declaration of the LCRB or HRRB, and on approval immediately issues the Notice of Award.
•The winning bidder formally enters into the contract within 10 calendar days from receipt of the Notice of Award.
•A higher approving authority has a maximum of 20 calendar days; a GOCC board acts within 30 calendar days from receipt.
•The Notice to Proceed is issued not later than 7 calendar days from approval of the contract; contract notices take effect only on receipt by the contractor.
•From bid opening to award the process may not exceed 3 months; a contract not acted on within the periods is deemed approved.
•If the LCRB or HRRB bidder fails to sign or to post the performance security, the BAC disqualifies it and post-qualifies the next-ranked bid; failure to post the performance security forfeits the bid security.
•For 5 years from effectivity, a provincial contractor whose lowest bid among provincial bidders is higher than an outside contractor's may match the outside bid.
•Every bid carries a sworn affidavit that the bidder and its officers are not related to the Head of the Procuring Entity by consanguinity or affinity up to the third civil degree; omitting it means automatic disqualification.
8 practice questions in the bank test this part.
A practice question on Section 37
Within what period must the Head of the Procuring Entity act on the BAC's recommendation of award under Section 37 of R.A. 9184?
AA period not exceeding fifteen calendar days (correct)
BSeven calendar days
CThirty calendar days
DNo period is fixed
Section 37 gives the Head of the Procuring Entity or a duly authorized representative a period not exceeding fifteen calendar days from the BAC's determination and declaration of the Lowest Calculated Responsive Bid or Highest Rated Responsive Bid to approve or disapprove the recommendation.
“Within a period not exceeding fifteen (15) calendar days from the determination and declaration by the BAC”
Section 48 allows the Procuring Entity, with the prior approval of its head and only where the Act's conditions are met, to use one of five alternative methods: Limited Source Bidding (Selective Bidding), Direct Contracting (Single Source Procurement), Repeat Order, Shopping and Negotiated Procurement. In every case the entity must obtain the most advantageous price for the government. Section 54 leaves the detailed terms to the IRR.
Sections 49 to 53 set the conditions for each. Questions describe a purchase and ask which method fits, or quote a threshold and ask which method it belongs to, so the conditions and the numbers both matter.
•Limited Source Bidding: direct invitation to pre-selected suppliers or consultants, only for highly specialised goods or consulting services obtainable from a limited number of sources, or major plant components where limiting bidders keeps a uniform level of quality.
•Direct Contracting: the supplier simply submits a price quotation or pro-forma invoice, only for proprietary goods protected by patents, trade secrets or copyright, critical components from a specific manufacturer needed to guarantee project performance, or goods from an exclusive dealer with no sub-dealers selling lower and no suitable substitute.
•Repeat Order: direct procurement from the previous winning bidder to replenish goods under a contract won by Competitive Bidding, provided for in the Annual Procurement Plan, at a unit price equal to or lower than the original, without splitting requisitions, within 6 months from the original Notice to Proceed, and not exceeding 25% of the quantity of each item.
•Shopping: price quotations for off-the-shelf goods, either for an unforeseen contingency needing immediate purchase not exceeding P50,000, or for ordinary office supplies and equipment not available in the Procurement Service not exceeding P250,000, without splitting contracts and with at least 3 quotations from bona fide suppliers. The GPPB may adjust the amounts.
•Negotiated Procurement: only after 2 failed biddings, in imminent danger to life or property during a state of calamity or where time is of the essence, in take-over of rescinded or terminated contracts, for contracts adjacent or contiguous to an ongoing infrastructure project under stated conditions, or for purchases from another government agency such as the Procurement Service of the DBM.
9 practice questions in the bank test this part.
A practice question on Section 48
By what other name does R.A. 9184 call Limited Source Bidding?
ASingle Source Procurement
BShopping
CRepeat Order
DSelective Bidding (correct)
Section 48 defines Limited Source Bidding, otherwise known as Selective Bidding, as a method involving direct invitation to bid from a set of pre-selected suppliers or consultants with known experience and proven capability.
“Limited Source Bidding, otherwise known as Selective Bidding”
Sections 55 to 58 set the protest mechanism. A BAC decision at any stage may be protested in writing to the head of the procuring entity, by a verified position paper and a non-refundable protest fee; the protest is resolved strictly on the BAC's records; it never stays or delays the bidding, but it must be resolved before any award; and court action is possible only after the protest is completed, before the regional trial court under Rule 65, with cases filed out of sequence dismissed for lack of jurisdiction.
Sections 59 and 60 send disputes arising from contract implementation to arbitration in the Philippines under R.A. 876, or to the Construction Industry Arbitration Commission where it is competent, with appeal to the Court of Appeals on pure questions of law. Section 61 fixes bid prices against escalation, and Section 62 sets the warranty rules for goods and for infrastructure.
•Protests go to the head of the procuring entity, in writing, by verified position paper with a non-refundable protest fee set in the IRR.
•The protest is resolved on the BAC's records alone; up to an amount set in the IRR the head's decision is final.
•No protest stays or delays the bidding, but protests must first be resolved before any award is made.
•Court action only after the protest is completed; the regional trial court has jurisdiction over the head's final decision, under Rule 65 of the 1997 Rules of Civil Procedure.
•Contract disputes go to arbitration under R.A. 876 (the Arbitration Law), or to the Construction Industry Arbitration Commission; the arbitral award is appealable to the Court of Appeals by petition for review on pure questions of law.
•Bid prices are fixed and not subject to escalation, except under extraordinary circumstances determined by NEDA and with prior GPPB approval.
•A contractor ordered to repair defects from inferior materials must do so within 90 days; failure brings perpetual disqualification from public bidding and attachment or garnishment of property.
6 practice questions in the bank test this part.
A practice question on Section 55
How must a protest against a decision of the BAC be made under Section 55 of R.A. 9184?
ABy filing a verified position paper and paying a non-refundable protest fee (correct)
BBy letter to the Commission on Audit
COrally at the bid opening
DBy filing a case directly with the regional trial court
Section 55 provides that decisions of the BAC may be protested to the head of the procuring entity in writing, by filing a verified position paper and paying a non-refundable protest fee.
“by filing a verified position paper and paying a non-refundable protest fee”
Offences, civil liability and administrative sanctions
Section 65 defines the criminal offences, all punished by imprisonment of not less than six years and one day but not more than fifteen years, without prejudice to R.A. 3019. Public officers are liable for opening sealed bids early, delaying the stages without cause, unduly influencing the BAC, splitting contracts, and abusing the power to reject bids in favour of a relative; private individuals for collusive bidding, sham competition through multiple entities, agreements to refrain from or withdraw bids, and other schemes that stifle competition, as well as for false eligibility documents, false bidding documents, bidding under another's name, and withdrawing a winning bid without just cause. Section 67 adds civil liability on conviction, and Section 68 requires a liquidated damages clause in every contract.
Section 69 lets the Head of the Procuring Entity, or the BAC by delegation, impose administrative suspension on bidders for listed violations, with forfeiture of the bid or performance security. Section 70 allows preventive suspension of BAC, Secretariat and Technical Working Group members on prima facie evidence, with due process. Sections 72 and 73 give BAC members private legal assistance and an indemnification package set by the GPPB.
•Criminal penalty for public officers and private individuals alike: imprisonment of not less than 6 years and 1 day but not more than 15 years, without prejudice to R.A. 3019.
•A public officer convicted also suffers temporary disqualification from public office; a private individual is permanently disqualified from transacting business with the government.
•Public-officer offences include opening sealed bids before the public opening, unjustified delay, undue influence on the BAC, splitting of contracts, and abusing the power to reject bids in favour of a relative under Section 47.
•Private-individual offences include pre-arranged bids, bidding through several entities to fake competition, agreements to refrain from bidding or withdraw bids, false eligibility or bidding documents, using another's name, and withdrawing a bid after it qualified as the lowest calculated or highest rated.
•When the bidder is a juridical entity, criminal liability falls on the directors, officers or employees who actually committed the act.
•Conviction carries civil liability: restitution for the damage, forfeiture of any unwarranted benefit, or both.
•Administrative penalty on bidders: suspension from public bidding of 1 year for the first offence and 2 years for the second, plus forfeiture of the bid or performance security; the head may delegate this to the BAC.
•A bidder has 7 calendar days to clarify or validate its bid in writing during post-qualification; refusal is a ground for suspension.
3 practice questions in the bank test this part.
A practice question on Section 65
An officer opens a sealed bid before the appointed time for public opening. How does R.A. 9184 treat this?
AAs a criminal offence carrying imprisonment of not less than six years and one day (correct)
BAs acceptable if no bidder objects
CAs an administrative lapse only
DAs a matter for the bidder to raise in a civil suit
Section 65 makes it an offence for a public officer to open any sealed bid, or divulge its contents, prior to the appointed time for the public opening, punishable by imprisonment of not less than six years and one day but not more than fifteen years.
“Open any sealed Bid including but not limited to Bids that may have been submitted through the electronic system and any and all documents required to be sealed or divulging their contents, prior to the appointed time for the public opening of Bids”
Common questions
What is R.A. 9184?
Republic Act No. 9184 is the Government Procurement Reform Act, approved on January 10, 2003. It governs the procurement of goods, infrastructure projects and consulting services by every branch and instrumentality of government, including GOCCs and local government units, under five principles: transparency, competitiveness, a streamlined process, accountability and public monitoring.
How many members does a Bids and Awards Committee have?
Under Section 11, at least five and not more than seven, chaired by at least a third ranking permanent official of the procuring entity other than its head. The approving authority may never be a member, and members serve a fixed, renewable term of one year.
What are the alternative methods of procurement under R.A. 9184?
Section 48 names five: Limited Source Bidding (Selective Bidding), Direct Contracting (Single Source Procurement), Repeat Order, Shopping and Negotiated Procurement. Each may be used only under the conditions in Sections 49 to 53, with the prior approval of the Head of the Procuring Entity, and the entity must still obtain the most advantageous price for the government.
What are the deadlines after the BAC recommends an award?
Under Section 37, the Head of the Procuring Entity acts within 15 calendar days and immediately issues the Notice of Award; the winning bidder signs the contract within 10 calendar days of receiving it; a higher approving authority has 20 calendar days and a GOCC board 30; and the Notice to Proceed is issued within 7 calendar days of contract approval. Section 38 caps the whole process from bid opening to award at three months.